|
Mill Creek Central
Trestle Tower Construction II
Status
9/06/2006, last updated
05/21/2007
The page describes the progress on
constructing after the construction of the first tower described
in Constructing Towers
I -
Getting Started.
| Status August 18,
2006:
The concrete slab closest to the camera is the abutment at the north
end of the trestle. The concrete had just been poured for
this and for tower 1,2 and 4 foundations. Tower 4 foundation is barely
visible beyond the completed tower 3. |
 |
| Status August 27, 2006: The
photo shows that we've cleaned up the debris between tower 3 and the
south abutment. Cribbing has been installed at the south
abutment and grading of the location of towers 5, 6 & 7 has been
completed. We'll be installing the forms for foundations 5, 6
& 7 next. |
 |
| Status August 31, 2006: The
photo at right was taken looking north from the south abutment.
Note that we've formed the foundations for the last three towers,
numbers 5, 6 & 7. Expect to pour the concrete after Labor
Day.
Photo below shows the tower assembly area at the
back of the steaming bay. Dick is looking over the just
completed center part of towers 1, 2 & 4. The welds have
been cleaned so all we have to do is paint the weld area and then
erect them. The stack of panels will be used on towers 5, 6 & 7
after they are cleaned and painted. |
 |
| Status September 5, 2006:
We've erected the center square part of towers1, 2 and 4. Photo
on right shows Scott Kuhn welding the legs of tower 4 to the base
channels. We erected tower 4 using the front loader on the
back hoe like we did for tower 3. Tower 4 was more difficult
because of a greater slope in the surrounding ground.
Randy Sutherland is disconnecting the strap between
the back hoe bucket and tower 1 in photo below. Tower 1 is
on a steep slope so we couldn't get the backhoe next to the foundation
as we did for towers 3 and 4. However, tower 1 is only 11 feet
tall so we lowered it from the north abutment.
Tower 2 was erected next. In that case we
positioned the backhoe down slope from the foundation and used a
chain from the hoe bucket to the midpoint of the tower to stand it up.
Note in photo below that we've added a
retaining wall to the north end. We need to pin the ties
together and put some dirt below the ties closest to the camera.
|
 |

| Status September 8, 2006:
The photo shows that we've finished the foundations for towers 5 , 6
and 7. The only concrete work to be done is to pour a pad on the
south abutment. Since the south abutment is fresh fill, we'll
probably wait till next spring to pout that pad. |
 |
| This is the view from the north end. Towers 1
and 3 are finished. The side legs for towers 2 and 4
are nearly assembled. Erection of those legs will be next.
We have a stack of painted panels ready to start assembling towers 5,
6 and 7.
At current pace, we can expect to be walking across some of the I
beams before the first snow. |
 |

Status September 21, 2006:
After ten days off we're back at it. Above photo shows that we
have all the steel up for towers 1 through 4. That is Jim Norris
tightening some of the nuts on the side legs of tower 4. We have to
add the braces to towers 1, 2 and 4 and the professional welders have to
finish the welding on some of the bases and the gussets at the top.
We're working on the last three towers which are shorter so the end of the
tower construction is in sight.

Status September 30, 2006: We worked really hard
this week and finished the fabrication of the remaining towers. We
erected the center part of towers 5 and 6 on Friday.
What a mess --- it had rained and the hillside was slick. We
used the backhoe to transport the core of tower 6 from the top of the
south side. Bigggggg mistake. The backhoe slid to the correct place to
drop the tower. We couldn't get it back up the hill and we were afraid
to let it slide down the hill --- those towers would be like
bowling pins. So --- dozer to the rescue and it pulled
the backhoe back
up the hill. We then were able to use the backhoe to set tower
5 on the foundation using the approach from the bottom through the mud
hole pictured above. We then tried to use the dozer to move
tower 6 up the hill slightly and buried it (the dozer).
The backhoe and a long cable came to the rescue.

On Saturday we tried a different approach to transport
the side legs for tower 5 ---- the Kubota tractor pictured above. It
has 4 wheel drive which helps some. Note that the dozer and backhoe are
taking a rest. Yes, the Kubota smokes a bit.
| We build the Jin-pole like device
pictured on right to hoist the tower sides into position. The pole
bolts to the tower cross angles through existing holes. The lower bolt can
be repositioned to swing the top to the other side. There is a
small manual wench mounted on the pole. It worked quite
well. This was a test. We now plan to build a second one and
use the pair to hoist the beams.
Note that the tower side is a few inches above
the top of the core. That's because the engineer made a minor error in
calculating the height of the side. Too tall is easy to fix ---- just
cut off the bottom of the legs. We did that using a
portable band saw while the side was hanging from the core as pictured. |
 |
| Dick is sitting down on the
job to adjust the base plates under the side legs. The tarp is
a futile attempt to keep dry and clean. The band saw
is in the red box setting on the stump in the background. The
saw was powered by the generator beside the stump.
|
 |
| This is the Status on September
30th. The photo was taken from the south abutment. The
side legs must be added to tower 6 and tower 7 must be erected.
Note that the channels on the tops of the towers
seem to have different heights ---- they do --- to accommodate the
three different beam heights.
Many of the tower legs are only tacked to the
base plates. The professional welders will stop by
in the next week or so and do the permanent welds. Also, the braces and
gussets between the side legs and the center legs must be added.
|
 |
|
Status October 3, 2006: That is
Bruce Werner making "professional" welds on the base of tower 7 ---
the last one! |
 |
| All the towers are up but we still
have to weld gussets at the top of some towers and to make final welds
between some tower legs and the base channels.
The red objects near the top of the first tower(
tower 1) are angle magnets. The magnets are holding the gussets
in place for the welder.
That is Wayne Godshall in blue making one
of those "professional" welds at the bottom of tower 2. (Wayne
was a little camera shy today ---- something about skipping school.)
|
 |

Photo above shows all 7 towers. The tower
construction is essentially complete so this page is complete.
The next part of the project is to install the beams ---- check out
Installing the Beams I.
|