April 20, 2014

Parking Area: The AEP contractors have finished the grading and seeding under the power lines. Sure hope to see green in the next couple weeks.

 

New Car Barn:  The roof trusses are in place --- roof is next.    Boy is that long!

 

Observation Deck: The deck is nearing completion.  All remains is to attach about half the deck boards.  Sure will be nice to see some green grass and leaves. 

 

Dan and Clee have been clearing the brush and small trees in the  area around the deck to enhance the view.  Nice job!

 

 

 

 

 