Yesterday the steaming bay was installed. Photo shows Heisler No2 on the steaming bay for a little maintenance at sunup today.
Today the electricians installed spotlights covering the switch and the steaming bay. The track crew also added to the siding that runs up the valley. The painters came and painted the switch and steaming bay steel.
This photo taken in the late afternoon shade shows the overall site. Ballast needs to be added to the two tracks on the right and gravel put around the building and steaming bay. The last task will be to put all the tools away and haul off the wood scraps. It's time to turn our full attention back to the logging line construction.